Catiline Creek Debris Flow Mitigation Service Project

Electoral Area C

Project overview

The Catiline Creek Debris Flow Mitigation Project is a major infrastructure initiative to design, construct, and establish operation and maintenance of a debris flow mitigation structure for the Catiline Creek at Lillooet Lake Estates. The objective of the project is to reduce the risk to the community and potential for loss of life by increasing capacity of the existing channel to manage future debris flows up to 100,000 cubic metres through the community, under a new forest service road bridge, and into Lillooet Lake. The SLRD is working closely with the Ministry of Forests to coordinate the Ministry’s replacement of the In-SHUCK-ch bridge over Catiline Creek in conjunction with the project. To learn more about the debris flow hazard, assessments and the SLRD Board’s "Do Not Occupy" Recommendation, visit the SLRD local hazard webpage for the Catiline Creek Debris Flow.

Location

Map of the project location.
Map of the LLE location.

Project timeline

 

2016  
  • Risk assessment and preliminary design
2022
  • LLE petition for service establishment and loan
  • Service establishment and loan bylaws adopted
  • Grant applications
2023
  • Community Emergency Preparedness Fund (CEPF) Grant confirmed
  • Began detailed design
  • Began permitting phase
2024
  • Investing in Canada Infrastructure Program Green Infrastructure Stream (ICIP-GreenARDM) Grant confirmed 
  • Completed detailed design
  • Permitting phase
2025
  • Tender Phase
  • Receipt of permits by owner
  • Contractor permitting applications
  • Construction begins
2026
  • Construction continues
  • Finalize operations and maintenance manual
  • Project close-out
  • Final survey for land tenure and statutory right of way (SRW)

Quick Stats

  • Budget: $11.697 million
  • Project Duration: 2023–2026
  • Current Phase: Construction began in Quarter 4 of 2025. Coastal Mountain Excavations Ltd. has been awarded the contract to serve as the General Contractor.
  • Funding: Provincial and federal funding + long-term borrowing from Lillooet Lake Estate residents: 
    • up to $5.697 million from the Green Infrastructure Stream of the Investing in Canada Infrastructure Program (ICIP) - a combined investment of $3.107 million from the federal government and $2.589 million from the provincial government.
    •  $2 million from the Province of B.C.’s Community Emergency Preparedness Fund (CEPF) Disaster Risk Reduction – Climate Adaptation stream
    • up to $4 million from Lillooet Lake Estates through a loan authorization bylaw adopted by the SLRD Board in 2022

Project Details

Project updates, staff reports and news releases

Project updates will be published here as available. 

Photo Gallery

This photo gallery shows past and current events related to the Catiline Creek Debris Flow Mitigation Project. 

Catiline Creek Debris Flow Mitigation project image in Area C, SLRD
2013 Debris Flow Event, Catiline Creek - August 30, 2013 (LLE)
2013 Debris Flow Event, Catiline Creek August 30 2013 (LLE)
2013 Debris Flow Event, Catiline Creek - August 30, 2013 (LLE)
Gate 4 Common Lot, Lillooet Lake Estates. Beside Catiline Creek. Project site visit. May 8 2023 (SLRD)
Gate 4 Common Lot, Lillooet Lake Estates. Project site visit - May 8, 2023 (SLRD)
Looking downstream Catiline Creek to Lillooet Lake from In-SHUCK-ch FSR Bridge. Project site visit. May 8 2023. (SLRD)
Looking downstream Catiline Creek to Lillooet Lake from In-SHUCK-ch FSR Bridge - May 8, 2023. (SLRD)
Looking upstream, Catiline Creek. Looking upstream, Catiline Creek. Gate 2 upper road. Project site visit. May 8 2023. (SLRD)
Looking upstream, Catiline Creek. Looking upstream, Catiline Creek. Gate 2 upper road - May 8, 2023 (SLRD)
6.5k site on In-SHUCK-ch FSR prepared to accept excavated materials. November 2025 (Capex) Work at 6.5k is funded and completed by Ministry of Forests as key project partner.
6.5k site on In-SHUCK-ch FSR prepared to accept excavated material. Work at 6.5k is funded and completed by Ministry of Forests as key project partner - November 2025 (Capex)
In-SHUCK-ch FSR bridge over Catiline Creek. November 3 2025 (SLRD)
In-SHUCK-ch FSR bridge over Catiline Creek - November 3, 2025 (SLRD)
Tree clearing, log sort. Catiline Creek. Upper Gate 6 November 18 2025 (LLE)
Tree clearing, log sort. Catiline Creek. Upper Gate 6 - November 18, 2025 (LLE)
Mouth of creek, showing silt curtain, common lot boat ramps, tree clearing. November 30 2025 (LLE)
Mouth of creek, showing silt curtain, common lot boat ramps, tree clearing - November 30, 2025 (LLE)
Silt Curtain at mouth of Creek December 2025 (LLE)
Silt curtain at mouth of creek - December 2025 (LLE)
November orthophoto, lower Catiline Creek. November 2025 (KWL)
November orthophoto, lower Catiline Creek. November 2025 (KWL)
December orthophoto, lower Catiline Creek. December 2025 (KWL)
December orthophoto, lower Catiline Creek - December 2025 (KWL)
January orthophoto, lower Catiline Creek - January 19, 2026 (KWL)
January orthophoto, lower Catiline Creek - January 19, 2026 (KWL)

2026 Construction - High-Level Overview

Focus on construction below the In-SHUCK-ch FSR

Completed

- Excavate the creek
- Build training berms
- Haul excavated materials to 6.5km road realignment project by Ministry of Forests

Install temporary bridge and bypass for In-SHUCK-ch FSR over Catiline Creek

Completed

Focus on construction through In-SHUCK-ch FSR right of way

Current

- Reroute traffic to new permanent bridge
- Excavate the creek
- Installation of new permanent FSR bridge (by Ministry of Forests)
- Remove temporary bridge and bypass

Focus on construction above the In-SHUCK-ch FSR 

Not completed

- Excavate the creek
- Build training berms

Final survey, Close Out

Not completed